Trade Permits

Building Official Trade Permits
  • A Trade Permit must be issued to each trade involved with construction before they can commence work.
  • There is no fee for a Trade Permit. All inspections are linked to your Permit.
  • A project specific Application Form is provided with each approved Land Use Permit.
  • Only Applications submitted electronically on that project-specific form will be accepted. Contact your project manager for a copy of this form.
What if I don't have a Land Use Permit?
  • Projects that require inspection but do not rise to the level of a Land Use Activity (e.g. replacement equipment) will be issued a Land Use Permit administratively under a facility's "Annual Permit." Contact Sue Stevens, (860) 396-7557, sstevens@mptn-nsn.gov
Submission
  • Completed forms can be saved for submittal utilizing the latest version of the freely available Adobe Reader. The completed form is then to be emailed to Sue Stevens at sstevens@mptn-nsn.gov. The contractor will in turn receive his permit by email when approved. The email will include a similar form to be utilized when requesting inspection.